Project Outlook: Projected Start Date: January 3, 2024 …
West Water Plant Improvements
PROJECT STATUS: The City received the final 100% design plans from McKim and Creed on …
Shade Structures Project – Wayside Park and Shoreline Fields
 Project Status: 5.29.24 The shades for the Shoreline Multi-Purpose Sports Field have …
Shade Structures Project – Wayside Park and Shoreline FieldsRead More
Montrose Outfall Dredge Project (H.Sally Fema Funded)
Project Outlook: February to July ♦ Contract has been fully executed and Notice to …
Montrose Outfall Dredge Project (H.Sally Fema Funded)Read More
Soundside Drive Septic to Sewer Project (Restore)
Project Outlook:Â --ITB bid Opening........................November 7th …
Wayfinding and Destination Signs
City of Gulf Breeze Destinations: 1. Shoreline Park 2. Vista Park 3. Woodland Park 4. …
New Elevated Water Tank Replacement
PROJECT STATUS: 7.10.24: The City had a progress meeting with McKim & Creed on …
Williamsburg Storm Drain Replacement
Williamsburg Drive Stormwater Improvements! Due to the damaging effects of Hurricane …
McClure Drive Sidewalk Replacement Project
Replacement of approximately 500 feet of sidewalk along McClure Drive. …