On January 5, 2021, City staff attended a project kick-off meeting with representatives …
South Santa Rosa Beneficial Reclaim Strategic Plan (BSRP) – Phase IIIRead More
On January 5, 2021, City staff attended a project kick-off meeting with representatives …
South Santa Rosa Beneficial Reclaim Strategic Plan (BSRP) – Phase IIIRead More
PROJECT STATUS: The bid opening was held on March 21, 2024. The city received 4 bids. …
PROJECT OUTLOOK AS OF JANUARY 8, 2024:Â On January 16, 2024, City Council approved the …
PROJECT STATUS: Pre-bid meeting scheduled for 3.26.2024 at 9:00 am. Bid opening: …
PROJECT STATUS: The Construction Contract is being executed by L&K and the City. …
PROJECT STATUS: 100% design plans have been submitted to the city for review. The next …
March 18, 2024 Update: 60% design plans submitted;Â 100% design plans expected 4.19.2024 …
PROJECT STATUS: Commencement Date: April 1, 2024 Site: Highpoint Work to be completed: …
Tennis Court Resurfacing and Pickleball Court ConstructionRead More
PROJECT STATUS: City Council awarded the bid to Soule Construction on March 4, 2024 in …