Montrose Outfall Dredge Project (H.Sally Fema Funded)
Questcdn:8364487
Scope of Work/ Specifications
- Project Inspection and Permitting
- A non-mandatory pre-bid will be held.
- Owner has secured all applicable permits. Contractor will be required to abide by permit requirements within the work area.
- Dredge Montrose Outfall
- Contractor is responsible for the placement and maintenance of sediment/erosion control necessary to comply with the USACE & FDEP permit for dredging.
- Perform a hydraulic or mechanical maintenance dredge to a depth of no more than 5 feet below the MLW and remove approximately 140 cubic yards of material from the mouth of Montrose Outfall.
- Dredging is not to exceed 140 cubic yards of sand.
- The dredged material will be discharged into an upland dredged material disposal cell with return water filtered through a water filtration system (if hydraulic dredging is utilized) or will be discharged into a container positioned on a barge located within the dredge area and dewatered within the limits of the turbidity barriers then hauled offsite to an upland dredged material disposal area (if mechanical dredging is utilized).
- Contractor shall have a pre and post-bathymetric survey performed on the dredged area by a licensed surveyor of the State of Florida.
- The project is located at Montrose Boulevard in Gilmore Bayou,
Latitude 30.361944° North, Longitude 87.187500° West, Section 6, Township 3 South,
Range 29 West, in Gulf Breeze, Santa Rosa County, Florida.
- Spoil Loading & Hauling
- Contractor is responsible for loading & hauling dredge spoil material from spoil site.
- Site Work Limitations
- Contractor will be responsible for MOT & residential accessibility to roadways and properties.
- Project work schedule will need to be phased with tide and depth of surrounding water to ensure access to the site is possible.
Project Milestones:
Milestone
Date
Notes
Bid Opening
02/07/2023
Awarded by City Council
02/21/2023
Notice of Intent to Award
02/22/2023
Notice of Award
02/28/2023
Contract Fully Executed-Signed
05/05/2023
date tbd as of 5/2/2023
Preconstruction Meeting
06/07/2023
Notice to Proceed
06/07/2023
Estimated Completion Date
10/05/2023
120 days from NTP