Shoreline Baseball Field Laser Grading
Last updated on July 27th, 2023 at 07:57 am
On October 17, 2022, the City Council approved the Advisory Park Board's recommendation in changing Field 9 infield from dirt to grass and to make all the infields dirt, for the purpose of accommodating tournaments and youth sports practices. The ballfields are scheduled for regrading and reseeding in order to address stormwater issues and play performance.
This project is budgeted through the Tourist Development Tax funds.
Total Estimated Cost: $30,000 | Advertising Date: 7.27.2023 - 08.03.2023
Project Milestones:
Milestone
Date
Notes
City Council approved project
10/17/2022
ITB
07/27/2023
Pre-Bid Meeting Date (Tentative)
08/23/2023
Bid Opening
09/05/2023
2:00 p.m.
Bid Awarded by Council (Tentative)
10/02/2023
Estimated Completion Date
02/29/2024