Utility Undergrounding Conversion Project
Last updated on August 24th, 2022 at 04:25 pm
CRA Sections A & B along Highway 98 - Utility Undergrounding Conversion - Design and Construction
Project Milestones:
Milestone
Date
Notes
Council Approval of PM Services Task Order
09/08/2021
Complete
Authorization to Proceed
10/20/2021
Complete
Council Approval of Professional Surveying - Additional Services
12/06/2021
Complete
Design Engineering
03/17/2022
In Progress
Construction Begins
09/30/2022
Upcoming
Project Completion
09/30/2024
Upcoming