Shoreline Field Synthetic Turf Project
Last updated on November 10th, 2022 at 03:06 pm
Shoreline Field will see yearlong tournaments and games starting this Fall. Last March 7th, 2022, the City Council approved the selection committee's recommendation for the selection of Hellas Construction Inc., of Austin Texas for the design-build services for artificial turf for Shoreline Field and authorized staff to negotiate a contract and fees with this firm.
Funding for the Sports & Tourism Project is from the City's tourism tax and a portion reimbursed by FEMA 80/20. Other amenities are sponsored in part by the Gulf Breeze Sports Association.
Project Milestones:
Milestone
Date
Notes
City Council Approved Selecting Committee's recomendations
03/07/2022
Contract Negotiations and City Council's Approval of Contract
04/18/2022
Design, Survey, Geotech, Permitting, Design Approval
05/24/2022
to June 26th
Notice to Proceed from City to Hellas
07/06/2022
Mobilization
07/18/2022
Earthwork & Grading, frame & pour concrete footer, install drainage system, final grading/earthwork
07/19/2022
to September 1st
Install felt layer & rock layer, grading of rock
09/01/2022
to September 30th (Weather Delays occurred)
Field Goal post, Time clocks, and Scoreboard delivered
09/09/2022
to September 22nd
Synthetic Turf Delivered
09/27/2022
Synthetic Turf laid out and cut
09/30/2022
Sand and Cushdrian Pad/ E-layer Shock Pad materials delivered
10/03/2022
to October 7th
19mm thick elastic rubber pad to be paved.
10/08/2022
to October 29th
Time Clocks & Scoreboard Installation
10/10/2022
to November 10th
Council considers change order to approve newly available EcoTherm in lieu of black rubber pellets for in-fill (applied on top of the turf)
10/17/2022
Synthetic Turf Installation/In-fill spread
10/31/2022
to November 12th
Original Completion Date
09/15/2022
Updated Completion Date
11/14/2022
Due to weather, supply delays and proposed change order to upgrade EcoTherm in lieu of rubber pellets