On May 15, 2023, City Council approved the new lighting agreement with Florida Power Light (FPL) for the Shoreline Park South parking lot and authorized the Mayor to execute the agreement upon review/approval of the City Attorney for legal sufficiency. The new agreement will allow the lighting to be leased for a single monthly fee and will remove the maintenance costs the city currently pays.
Total Project Estimate: $30,000
Project Milestones:
Milestone: City Council signed agreement with FPL
Date: 05/15/2023
Milestone: Pre-Bid Meeting
Date: 06/05/2023
Milestone: Completion Date
Date: 10/02/2023